PressCenter.com  - Free Press Release Distribution Platform
No Result
View All Result
Thursday, November 12, 2026
  • Login
  • Register
  • Home
  • Categories
    • Art & Culture
    • Business & Entrepreneurship
    • Economy & Finances
    • Education & Parenting
    • Energy & Environment
    • Government & Politics
    • Health & Beauty
    • Internet & IT
    • Lifestyle & Fashion
    • Media & Social Networks
    • Society & Welfare
    • Sport & Leisure
    • Technology & Science
    • Traffic & Safety
    • Work & Career
  • Countries
    • Belgium
    • Europe
    • France
    • Germany
    • International
    • Luxembourg
    • Netherlands
    • Others
    • Russia
    • UK
  • Service Portal
    • Press Release Distribution
    • My Press Releases
    • Add Press Release – FREE
    • Service Packs
ADD PRESS RELEASE
PressCenter.com  - Free Press Release Distribution Platform
  • Home
  • Categories
    • Art & Culture
    • Business & Entrepreneurship
    • Economy & Finances
    • Education & Parenting
    • Energy & Environment
    • Government & Politics
    • Health & Beauty
    • Internet & IT
    • Lifestyle & Fashion
    • Media & Social Networks
    • Society & Welfare
    • Sport & Leisure
    • Technology & Science
    • Traffic & Safety
    • Work & Career
  • Countries
    • Belgium
    • Europe
    • France
    • Germany
    • International
    • Luxembourg
    • Netherlands
    • Others
    • Russia
    • UK
  • Service Portal
    • Press Release Distribution
    • My Press Releases
    • Add Press Release – FREE
    • Service Packs
No Result
View All Result
PressCenter.com  - Free Press Release Distribution Platform
No Result
View All Result
Home Sources Business & Entrepreneurs

RWE: Inter-array cabling for Nordsee Ost offshore wind farm completed ahead of schedule

by PressCenter.com
June 16, 2014
in Business & Entrepreneurs, Categories, Countries, Energy & Environment, Figures, Others, Sources, Special
0
1.2k
SHARES
2k
VIEWS
Share on FacebookShare on TwitterLinkedIn
ADVERTISEMENT
  • More than 60 kilometres of cable laid
  • Work carried out by Visser & Smit Marine Contracting
  • Two special cable-laying vessels in operation

“We divided cable installation into two campaigns. The first 30 kilometres of cable or so were already installed and buried in the seabed last year. This took off some of the time pressure from the most intricate process. The remaining cables were laid over the last few weeks”, explained Marcel Sunier, Project Director for Nordsee Ost at RWE Innogy. “The team did an excellent job. They completed the work around two weeks ahead of the original schedule.” The cable work was carried out by the Dutch company Visser & Smit Marine Contracting.

All 48 foundations for the wind turbines and the foundation of the substation were connected with each other by so-called inter-array cables. The 33-kilovolt underwater cables have a diameter of up to 16 centimetres. A particularly robust sheathing protects the cables from the extreme stresses caused in particular by the installation process out at sea. At the same time, they guarantee maximum power transmission across large distances. Special-purpose cable laying vessels were used to install these high-capacity power lines.

Two of these special installation vessels, the “Normand Flower” (in 2013) and the “Stemat Spirit ” (in 2014) were in operation at the Nordsee Ost wind farm. At the port of Landskrona, Sweden, they took up to 30 kilometres of cable on board before taking off to the wind farm’s construction field. Upon arrival, they connected twelve foundations in a so-called loop each time. For this purpose, the cables first had to be cut to the right length, which was done on board. Subsequently, the cable ends were pulled into the cable tunnels provided in the foundation where they were fastened. The cables connecting the individual foundations were buried at a depth of around 1 ½ metres in the seabed. Subsequently, diving robots, so-called remotely operated vehicles (ROVs), surveyed the final cable position and checked the proper functioning of the cables laid.

In August the inter-array cables will be connected with the offshore substation, the nerve centre of the wind farm. The substation transforms the electricity generated by the wind turbines at 33 kilovolts to a transmission voltage of 155 kilovolts so that the electricity can be transmitted via high-voltage undersea cables to the coast. The substation of the Nordsee Ost wind farm is around 15 m high and weighs approx. 2,000 tons. Like the wind turbines, it is mounted on a steel structure foundation in the seabed and will tower around 35 metres above sea level after final assembly. The steel foundation which weighs around 700 tons was already installed in July 2013. The actual substation platform (topside) is to follow in mid-July.

The 48 foundations for the wind turbines at the Nordsee Ost wind farm were completed in mid-March 2014. In May, construction started on the wind turbines. After their completion, scheduled for spring 2015, the Nordsee Ost offshore wind farm will have an installed capacity of around 295 MW and supply an equivalent of some 300,000 households with electricity every year. Equipped with the currently most powerful offshore turbines, Nordsee Ost is one of the largest commercial wind power projects off the German coast.

ADVERTISEMENT
Tags: Nordsee OstOffshore Wind Farmpress releasevessels
ADVERTISEMENT
ADVERTISEMENT
FasterCapital’s EquityPilot to help shape Pacific region’s major cultural attraction
Business & Entrepreneurship

FasterCapital’s EquityPilot to help shape Pacific region’s major cultural attraction

by Press Center Editor
November 11, 2026
0

Fiji’s tourism economy is seeking high-value, experience-led offerings beyond its resort and beach product. With 929,740 international visitors in 2023...

Read moreDetails
AI Integration Services in 2026: How Connected AI Ecosystems, Intelligent APIs, and Real-Time Data Are Transforming Businesses

AI Integration Services in 2026: How Connected AI Ecosystems, Intelligent APIs, and Real-Time Data Are Transforming Businesses

November 11, 2026
KWT Spider 3.0 Helps Website Owners Find Technical SEO Issues Through Website Crawling

KWT Spider 3.0 Helps Website Owners Find Technical SEO Issues Through Website Crawling

November 11, 2026
PCDOTS Introduces a Windows Utility for Managing Multiple CSV Files in One Place

PCDOTS Introduces a Windows Utility for Managing Multiple CSV Files in One Place

November 11, 2026
Rivira Systems Strengthens Business Transformation with Expert Business Central Migration Services

Rivira Systems Strengthens Business Transformation with Expert Business Central Migration Services

November 11, 2026
PressCenter.com  - Free Press Release Distribution Platform

PressCenter.com is state-of-the-art Press Release Distribution Platform. PressCenter.com send and track your Press Release using our industry-leading global Media Contacts Database of a million contacts. Your Press Release will reach business news editors and journalists, in targeted sectors and territories or worldwide.

Policies

  • Terms & Conditions
  • Copyrights
  • Cookies
  • Disclaimer
  • Privacy Policy

Services

  • Home
  • Press Release Distribution
  • Add Press Release – FREE
  • Guidelines
  • Advertisement
  • About Us
  • Contact Our Team

Press Releases by E-Mail

To stay on top of the ever-changing world of business, subscribe now to our newsletters.

*We hate spam as you do.

Categories

© 1998-2025 PressCenter.com - Latest Business News and Press Releases

Welcome Back!

Login to your account below

Forgotten Password? Sign Up

Create New Account!

Fill the forms below to register

All fields are required. Log In

Retrieve your password

Please enter your username or email address to reset your password.

Log In
No Result
View All Result
  • Home
  • Press Release Distribution
  • Add Press Release – FREE
  • Advertisement
  • Contact Our Team
  • Guidelines
  • About Us

© 1998-2025 PressCenter.com - Latest Business News and Press Releases