The project involves constructing the second artificial island in the Pacific Ocean off the densely populated shoreline of Panama City. Nine hectares of land will be created by using approximately 600,000 cubic meters of rock to form a perimeter and filling it with 1.3 million cubic meters of sand. A bridge will be built to connect the second island to the first island.
The client Compañía Insular Americana, S.A. is an affiliated company of Ocean Reef Island Inc for which Boskalis constructed the first artificial island.
Boskalis will use tugboats and barges to transport the rock and a clamshell and excavators to install the rock perimeter. Thereafter, the island will be filled with sand supplied by a large trailing suction hopper dredger.
Boskalis’ strategy is aimed at benefitting from key macro-economic factors which drive worldwide demand in our markets: expansion of the global economy, increasing energy consumption, global population growth and the challenges presented by climate change. This land reclamation project is driven by the necessity to create land to accommodate population growth in a densely populated region.